What is the concern of the Dorchester,Ltd case

Sagot :

Answer:

It was concerned that the date for its response of 28 January 2008 was only 18 working days after 5 January and was simply not long enough to respond to the detailed claim submitted given the new evidence and revised figures. The Dorchester therefore sought declarations from the Court through Part 8 proceedings that:

"there is a serious risk of a breach of natural justice in the conduct of the adjudication … and, unless the parties agree a realistic timetable …, any decision issued by the Adjudicator against the existing timetable … would be unenforceable by reason of breach of natural justice".

Explanation:

hope it helps..keep safe po